Namo Whispering Bliss, Malad East

by Parvati Madhav Realty LLP · Malad East, Mumbai 400097 · Map

Launched
Oct 20266 yrs 2 mths promised
Possession (MahaRERA)
Dec 2032Not extended
Concrete structure
0%Early stage
Booked (free sale)
86 of 15954% · 7 rehab units
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale86 booked out of 159 units

Rehab7 units for existing members

Total 166 units. Rehab units are not for sale.

Project facts

1 BHK
86
2 BHK
39
3 BHK
20
Other units
21
Total units
166
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0
Free-sale units
159
Rehab units
7
Reserved units
86

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%86

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400097

Projects with 70–300 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400097
MeasureThis projectSimilar projects
Launch to possession (as first promised)6 yrs 2 mths3 yrs 6 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Dec 2032Dec 2029
Concrete structure (RCC)0%0%
Units booked (free sale)54%0%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Namo Whispering Bliss by Parvati Madhav Realty LLP is a 166-unit SRA-sanctioned project in Malad East, Mumbai 400097, launched in October 2026 with possession due in December 2032. 86 units booked out of 159 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Namo Whispering Bliss is an SRA-sanctioned project by Parvati Madhav Realty LLP in Malad East, Mumbai 400097, registered with MahaRERA as PM1180002602118. It was launched in October 2026. It has 166 units in 1 building: 145 homes (1, 2 and 3 BHK) and 21 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 166 units, 159 are for sale and 7 are rehab units for existing members.

Its registered possession date is December 2032, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

86 units booked out of 159 units for sale (54%).