Ventara Heights, Malad East

by Shree Jaliyan Realty Venture LLP · Malad East, Mumbai 400097 · Map

Launched
Jun 20263 yrs 6 mths promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
0%Early stage
Booked (free sale)
0 of 640% · 19 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 64 units

Rehab19 units for existing members

Total 83 units. Rehab units are not for sale.

Project facts

1 BHK
38
2 BHK
36
Other units
9
Total units
83
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
64
Rehab units
19

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation0%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Work not started as of Oct 2026

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%0
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400097

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400097
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 6 mths5 yrs
Possession date extendedNo0 of 4
Possession date (MahaRERA)Dec 2029Jun 2031
Concrete structure (RCC)0%0%
Units booked (free sale)0%27%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Ventara Heights by Shree Jaliyan Realty Venture LLP is an 83-unit SRA-sanctioned project in Malad East, Mumbai 400097, launched in June 2026 with possession due in December 2029. 0 units booked out of 64 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Ventara Heights is an SRA-sanctioned project by Shree Jaliyan Realty Venture LLP in Malad East, Mumbai 400097, registered with MahaRERA as PR1180002600978. It was launched in June 2026. It has 83 units in 1 building: 74 homes (1 and 2 BHK) and 9 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 83 units, 64 are for sale and 19 are rehab units for existing members.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started.

0 units booked out of 64 units for sale (0%).