7 Mahalaxmi, Lower Parel
by Runwal Real Estates Private Limited · Lower Parel, Mumbai 400013 · Map
- Launched
- Sep 2024First of 2 phases
- Possession (MahaRERA)
- Oct 2031 – Sep 2034Not extended
- Concrete structure
- 0%Weighted across 2 phases
- Booked
- 134 of 63921%
- Buildings
- 25.6 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 167
- 3 BHK
- 279
- 4 BHK
- 187
- 5+ BHK
- 6
- Total units
- 639
- Buildings
- 2
- Land
- 5.6 acres
- Phases
- 2
- MahaRERA complaints
- 0
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| 7 Mahalaxmi - Tower 1 Early stage | PR1170002400011 | 271 | 0% | 49% | |
| 7 Mahalaxmi - Tower 3 Early stage | PR1172022600440 | 368 | 0% | 0% |
Show updates by phase
7 Mahalaxmi - Tower 1 (PR1170002400011)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | 134 | |
| 0% | 0% | 0% | 134 | |
| 0% | 0% | 0% | 0 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
7 Mahalaxmi - Tower 3 (PR1172022600440)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | 0 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Work not started as of Oct 2026
About this project
7 Mahalaxmi by Runwal Real Estates Private Limited is a 639-unit BMC-sanctioned project in Lower Parel, Mumbai 400013, registered with MahaRERA in 2 phases, with possession dates from October 2031 to September 2034. 134 units booked out of total 639 units. Work on the concrete structure (RCC) has not started.
Read full summary
7 Mahalaxmi is a BMC-sanctioned project by Runwal Real Estates Private Limited in Lower Parel, Mumbai 400013, registered with MahaRERA as 2 phases (PR1170002400011, PR1172022600440). The first phase was launched in September 2024. Together the phases have 639 units in 2 buildings, with 2, 3, 4 and 5+ BHK homes as registered with MahaRERA. Both phases are active on MahaRERA.
The phases' registered possession dates run from October 2031 to September 2034; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 0% complete and final finishes 0% complete. Neither phase has its structure complete.
134 units booked out of total 639 units (21%).
Runwal's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 46 |
|---|---|
| Total units across these projects | 14,623 |
| Completed without extending the possession date | 10 |
| Completed after an extension | 5 |
| Lapsed | 5 |
| Under construction | 26 |
| Possession date extended on the builder's application | 16 |
| Typical time from launch to 100% structure | 7 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Runwal projects | 343 (35 of 46 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.