by Harsh Developers & Infrastructure LLP · Dadar West, Mumbai 400028 · Map

Launched
Mar 20263 yrs 1 mth promised
Possession (MahaRERA)
Apr 2029Not extended
Concrete structure
0%Early stage
Booked (free sale)
2 of 248% · 2 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale2 booked out of 24 units

Rehab2 units for existing members

Land-owner share11 units, not for sale

Total 37 units. Rehab and land-owner units are not for sale.

Project facts

1 BHK
11
2 BHK
20
3 BHK
6
Total units
37
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
24
Rehab units
2
Land-owner share (not for sale)
11

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 40%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%2
40%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400028

Projects with 10–80 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400028
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 1 mth2 yrs 11 mths
Possession date extendedNo0 of 5
Possession date (MahaRERA)Apr 2029Dec 2028
Concrete structure (RCC)0%10%
Units booked (free sale)8%0%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Harsh Aurum by Harsh Developers & Infrastructure LLP is a 37-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in March 2026 with possession due in April 2029. 2 units booked out of 24 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Harsh Aurum is a BMC-sanctioned project by Harsh Developers & Infrastructure LLP in Dadar West, Mumbai 400028, registered with MahaRERA as PR1170002502696. It was launched in March 2026. It has 37 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 37 units, 24 are for sale, 2 are rehab units for existing members and 11 are the land-owner's share, not for sale.

Its registered possession date is April 2029, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

2 units booked out of 24 units for sale (8%). Since the July 2026 update, 2 more units have been booked.