Adityaraj Midtown, Dadar West
by Kent Corporation · Dadar West, Mumbai 400028 · Map
- Launched
- Oct 20252 yrs 8 mths promised
- Possession (MahaRERA)
- Jun 2028Not extended
- Concrete structure
- 18%Mid-construction
- Booked (free sale)
- 5 of 2917% · 33 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale5 booked out of 29 units
Rehab33 units for existing members
Total 62 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 39
- 2 BHK
- 16
- 3 BHK
- 3
- Other units
- 4
- Total units
- 62
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 29
- Rehab units
- 33
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 18% | 0% | 5 | |
| 100% | 0% | 0% | – | |
| 0% | 0% | 0% | – |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400028
Projects with 20–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 8 mths | 3 yrs 11 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Jun 2028 | Aug 2029 |
| Concrete structure (RCC) | 18% | 5% |
| Units booked (free sale) | 17% | 12% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Dipti Opal Bay, Dadar West
- Yashwant Heights, Dadar West
- Suraj Aureva, Dadar West
- Park View Residency, Dadar West
- Saffron, Dadar West
- Harsh Aurum, Dadar West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Dipti Opal Bay | August 2025 | December 2029 | 20% | 0 units booked out of 15 units for sale |
| Yashwant Heights | December 2025 | December 2030 | 10% | 2 units booked out of 13 units for sale |
| Suraj Aureva | July 2025 | December 2031 | 0% | 19 units booked out of 26 units for sale |
| Park View Residency | January 2026 | December 2028 | 15% | 0 units booked out of 14 units for sale |
| Saffron | June 2025 | December 2028 | 0% | 6 units booked out of 18 units for sale |
| Harsh Aurum | March 2026 | April 2029 | 0% | 2 units booked out of 24 units for sale |
About this project
Adityaraj Midtown by Kent Corporation is a 62-unit BMC-sanctioned project in Dadar West, Mumbai 400028, launched in October 2025 with possession due in June 2028. 5 units booked out of 29 units for sale. The concrete structure (RCC) is 18% complete.
Read full summary
Adityaraj Midtown is a BMC-sanctioned project by Kent Corporation in Dadar West, Mumbai 400028, registered with MahaRERA as P51900080996. It was launched in October 2025. It has 62 units in 1 building: 58 homes (1, 2 and 3 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 62 units, 29 are for sale and 33 are rehab units for existing members.
Its registered possession date is June 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 18% complete, final finishes not started.
5 units booked out of 29 units for sale (17%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 18%.