Aureus, Sewri
by Lodha Developers Limited · Sewri, Mumbai 400015 · Map
- Launched
- Mar 20266 yrs 9 mths promised
- Possession (MahaRERA)
- Dec 2032Not extended
- Concrete structure
- 0%Early stage
- Booked
- 0 of 3540%
- Buildings
- 25.9 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 3 BHK
- 196
- 4 BHK
- 154
- Other units
- 4
- Total units
- 354
- Buildings
- 2
- Land
- 5.9 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Work not started as of Oct 2026
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | 0 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Aureus by Lodha Developers Limited is a 354-unit SRA-sanctioned project in Sewri, Mumbai 400015, launched in March 2026 with possession due in December 2032. 0 units booked out of total 354 units. Work on the concrete structure (RCC) has not started.
Read full summary
Aureus is an SRA-sanctioned project by Lodha Developers Limited in Sewri, Mumbai 400015, registered with MahaRERA as PR1170002502863. It was launched in March 2026. It has 354 units in 2 buildings: 350 homes (3 and 4 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is December 2032, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started.
0 units booked out of total 354 units (0%).
Lodha's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 85 |
|---|---|
| Total units across these projects | 15,101 |
| Completed without extending the possession date | 31 |
| Completed after an extension | 13 |
| Lapsed | 0 |
| Under construction | 41 |
| Possession date extended on the builder's application | 34 |
| Typical time from launch to 100% structure | 5 years 10 months |
| MahaRERA complaints (filed by or against the builder), all Lodha projects | 242 (38 of 85 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.