Skip to main content

Parimal Heritage, Borivali East

by Dvnm Realty Private Limited · Borivali East, Mumbai 400066 · Map

Launched
Oct 20242 yrs 5 mths promised
Possession (MahaRERA)
Mar 2027Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
6 of 967% · 13 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale6 booked out of 9 units

Rehab13 units for existing members

Total 22 units. Rehab units are not for sale.

Project facts

1 RK
1
2 BHK
16
3 BHK
5
Total units
22
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
9
Rehab units
13

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services85%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 0%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 90%Jul 2026: Concrete structure (RCC) 40%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 85%Excavation 100%Concrete structure (RCC) 100%Final finishes 85%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%85%6
100%40%0%5
100%90%0%4
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400066

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400066
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 5 mths3 yrs
Possession date extendedNo1 of 6
Possession date (MahaRERA)Mar 2027Nov 2027
Concrete structure (RCC)100%60%
Units booked (free sale)67%54%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Parimal Heritage by Dvnm Realty Private Limited is a 22-unit BMC-sanctioned project in Borivali East, Mumbai 400066, launched in October 2024 with possession due in March 2027. 6 units booked out of 9 units for sale. The concrete structure (RCC) is complete.

Read full summary

Parimal Heritage is a BMC-sanctioned project by Dvnm Realty Private Limited in Borivali East, Mumbai 400066, registered with MahaRERA as PR1180002400088. It was launched in October 2024. It has 22 units in 1 building, with 1 RK, 2 BHK and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 22 units, 9 are for sale and 13 are rehab units for existing members.

Its registered possession date is March 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 85% complete.

6 units booked out of 9 units for sale (67%). Since the July 2026 update, 1 more unit has been booked and the reported concrete structure (RCC) has gone from 40% to 100%.