Jayhari Chs Ltd, Borivali East
by Dam Builders And Developers · Borivali East, Mumbai 400066 · Map
- Launched
- Apr 20241 yr 8 mths originally promised
- Possession (MahaRERA)
- Apr 2027Extended by 1 yr 4 mths
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 20 of 2580% · 9 rehab units
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale20 booked out of 25 units
Rehab9 units for existing members
Total 34 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 31
- Other units
- 3
- Total units
- 34
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 25
- Rehab units
- 9
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 20 | |
| 100% | 100% | 0% | 20 | |
| 100% | 60% | 0% | – | |
| 100% | 20% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400066
Projects with 10–70 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 1 yr 8 mths | 3 yrs 2 mths |
| Possession date extended | By 1 yr 4 mths | 1 of 6 |
| Possession date (MahaRERA) | Apr 2027 | Nov 2027 |
| Concrete structure (RCC) | 100% | 56% |
| Units booked (free sale) | 80% | 65% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Vasant Heritage, Borivali East
- Adinath Heights, Borivali East
- Trilok Giriraj Kripa, Borivali East
- Sanghvi Horizon, Borivali East
- Parimal Heritage, Borivali East
- 66 Aventus Avenue, Borivali East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Vasant Heritage | April 2024 | December 2026 | 66% | 13 units booked out of 18 units for sale |
| Adinath Heights | February 2024 | March 2026 | 100% | 13 units booked out of total 20 units |
| Trilok Giriraj Kripa | August 2024 | July 2028 | 40% | – |
| Sanghvi Horizon | December 2023 | December 2028 | 21% | 3 units booked out of total 22 units |
| Parimal Heritage | October 2024 | March 2027 | 100% | 6 units booked out of 9 units for sale |
| 66 Aventus Avenue | October 2024 | December 2029 | 45% | 8 units booked out of 20 units for sale |
About this project
Jayhari Chs Ltd by Dam Builders And Developers is a 34-unit BMC-sanctioned project in Borivali East, Mumbai 400066, launched in April 2024 with possession due in April 2027. 20 units booked out of 25 units for sale. The concrete structure (RCC) is complete.
Read full summary
Jayhari Chs Ltd is a BMC-sanctioned project by Dam Builders And Developers in Borivali East, Mumbai 400066, registered with MahaRERA as P51800055510. It was launched in April 2024. It has 34 units in 1 building: 31 homes (1 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 34 units, 25 are for sale and 9 are rehab units for existing members.
Its registered possession date is April 2027, extended by 1 year 4 months from the original December 2025. Construction: excavation complete, structure (RCC) complete, final finishes not started.
20 units booked out of 25 units for sale (80%).