Skip to main content

Snow White A Building Chs Ltd, Bandra West

by Shree Riddhi Siddhi Real Ventures LLP · Bandra West, Mumbai 400050 · Map

Launched
Jun 20252 yrs 10 mths promised
Possession (MahaRERA)
Apr 2028Not extended
Concrete structure
46%Mid-construction
Booked (free sale)
0 of 110% · 10 rehab units
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 11 units

Rehab10 units for existing members

Total 21 units. Rehab units are not for sale.

Project facts

2 BHK
10
3 BHK
9
5+ BHK
2
Total units
21
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
11
Rehab units
10

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)46%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 46%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 46%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%46%0%0
100%0%0%0
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400050

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400050
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 10 mths4 yrs
Possession date extendedNo1 of 6
Possession date (MahaRERA)Apr 2028Jul 2029
Concrete structure (RCC)46%0%
Units booked (free sale)0%21%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Snow White A Building Chs Ltd by Shree Riddhi Siddhi Real Ventures LLP is a 21-unit BMC-sanctioned project in Bandra West, Mumbai 400050, launched in June 2025 with possession due in April 2028. 0 units booked out of 11 units for sale. The concrete structure (RCC) is 46% complete.

Read full summary

Snow White A Building Chs Ltd is a BMC-sanctioned project by Shree Riddhi Siddhi Real Ventures LLP in Bandra West, Mumbai 400050, registered with MahaRERA as PR1180002500124. It was launched in June 2025. It has 21 units in 1 building, with 2, 3 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 21 units, 11 are for sale and 10 are rehab units for existing members.

Its registered possession date is April 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 46% complete, final finishes not started.

0 units booked out of 11 units for sale (0%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 46%.