Bandstand Cama, Bandra West
by Imperial Infradevelopers Private Limited · Bandra West, Mumbai 400050 · Map
- Launched
- Oct 20254 yrs 3 mths originally promised
- Possession (MahaRERA)
- Apr 2032Extended by 2 yrs 3 mths
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 3 of 2512% · 1 rehab units
- Buildings
- 11 acre
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale3 booked out of 25 units
Rehab1 unit for existing members
Total 26 units. Rehab units are not for sale.
Project facts
- 5+ BHK
- 24
- Other units
- 2
- Total units
- 26
- Buildings
- 1
- Land
- 1 acre
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 25
- Rehab units
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 98% | 0% | 0% | 3 | |
| 85% | 0% | 0% | 2 | |
| 85% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400050
Projects with 10–50 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 3 mths | 3 yrs 2 mths |
| Possession date extended | By 2 yrs 3 mths | 0 of 5 |
| Possession date (MahaRERA) | Apr 2032 | Dec 2028 |
| Concrete structure (RCC) | 0% | 0% |
| Units booked (free sale) | 12% | 20% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- Mio Miraya, Bandra West
- Crest 4 Pali Hill, Bandra West
- Paradigm Superstar, Bandra West
- Zahra, Bandra West
- Snow White A Building Chs Ltd, Bandra West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Mio Miraya | October 2025 | December 2028 | 0% | 3 units booked out of 13 units for sale |
| Crest 4 Pali Hill | September 2025 | May 2029 | 0% | 1 unit booked out of 5 units for sale |
| Paradigm Superstar | November 2025 | March 2029 | 0% | 0 units booked out of 21 units for sale |
| Zahra | December 2025 | December 2028 | 29% | 15 units booked out of 21 units for sale |
| Snow White A Building Chs Ltd | June 2025 | April 2028 | 46% | 0 units booked out of 11 units for sale |
About this project
Bandstand Cama by Imperial Infradevelopers Private Limited is a 26-unit SRA-sanctioned project in Bandra West, Mumbai 400050, launched in October 2025 with possession due in April 2032. 3 units booked out of 25 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Bandstand Cama is an SRA-sanctioned project by Imperial Infradevelopers Private Limited in Bandra West, Mumbai 400050, registered with MahaRERA as PR1180002501131. It was launched in October 2025. It has 26 units in 1 building: 24 homes (5+ BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 26 units, 25 are for sale and 1 is a rehab unit for existing members.
Its registered possession date is April 2032, extended by 2 years 3 months from the original January 2030. Construction: excavation 98% complete, structure (RCC) not started, final finishes not started.
3 units booked out of 25 units for sale (12%). Since the July 2026 update, 1 more unit has been booked and the possession date has moved from January 2030 to April 2032.