Axiom Rudra, Goregaon West
by Axiom Refab Construction (India) Pvt Ltd · Goregaon West, Mumbai 400104 · Map
- Launched
- Jul 20254 yrs 8 mths promised
- Possession (MahaRERA)
- Mar 2030Not extended
- Concrete structure
- 25%Mid-construction
- Booked (free sale)
- 30 of 9831%
- Buildings
- 20.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale30 booked out of 98 units
Land-owner share40 units, not for sale
Total 138 units. Land-owner units are not for sale.
Project facts
- 3 BHK
- 138
- Total units
- 138
- Buildings
- 2
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 98
- Land-owner share (not for sale)
- 40
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 25% | 0% | 30 | |
| 100% | 0% | 0% | 19 | |
| 50% | 0% | 0% | – |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400104
Projects with 60–300 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 8 mths | 3 yrs 10 mths |
| Possession date extended | No | 1 of 4 |
| Possession date (MahaRERA) | Mar 2030 | Feb 2029 |
| Concrete structure (RCC) | 25% | 28% |
| Units booked (free sale) | 31% | 52% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Ariha Skyes, Goregaon West
- 38 Avenue, Goregaon West
- Ashirwad Avenue, Goregaon West
- 5th Avenue SunteckCity - Tower 2, Goregaon West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Ariha Skyes | May 2025 | March 2029 | 51% | 32 units booked out of 42 units for sale |
| 38 Avenue | March 2025 | January 2029 | 6% | 28 units booked out of 72 units for sale |
| Ashirwad Avenue | January 2025 | December 2028 | 100% | 51 units booked out of 78 units for sale |
| 5th Avenue SunteckCity - Tower 2 | January 2026 | December 2032 | 0% | 29 units booked out of total 285 units |
About this project
Axiom Rudra by Axiom Refab Construction (India) Pvt Ltd is a 138-unit MHADA-sanctioned project in Goregaon West, Mumbai 400104, launched in July 2025 with possession due in March 2030. 30 units booked out of 98 units for sale. The concrete structure (RCC) is 25% complete.
Read full summary
Axiom Rudra is a MHADA-sanctioned project by Axiom Refab Construction (India) Pvt Ltd in Goregaon West, Mumbai 400104, registered with MahaRERA as PR1180002500205. It was launched in July 2025. It has 138 units in 2 buildings, with 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 138 units, 98 are for sale and 40 are the land-owner's share, not for sale.
Its registered possession date is March 2030, unchanged since launch. Construction: excavation complete, structure (RCC) 25% complete, final finishes not started.
30 units booked out of 98 units for sale (31%). Since the July 2026 update, 11 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 25%.