Ariha Skyes, Goregaon West
by Ariha Globe LLP · Goregaon West, Mumbai 400104 · Map
- Launched
- May 20253 yrs 10 mths promised
- Possession (MahaRERA)
- Mar 2029Not extended
- Concrete structure
- 51%Mid-construction
- Booked (free sale)
- 32 of 4276% · 46 rehab units
- Buildings
- 10.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale32 booked out of 42 units
Rehab46 units for existing members
Total 88 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 34
- 2 BHK
- 1
- 3 BHK
- 21
- 4 BHK
- 21
- Other units
- 11
- Total units
- 88
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 42
- Rehab units
- 46
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 51% | 0% | 32 | |
| 100% | 38% | 0% | 22 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400104
Projects with 30–200 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 10 mths | 3 yrs 10 mths |
| Possession date extended | No | 0 of 5 |
| Possession date (MahaRERA) | Mar 2029 | Dec 2028 |
| Concrete structure (RCC) | 51% | 100% |
| Units booked (free sale) | 76% | 46% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 5 projects
- 38 Avenue, Goregaon West
- Hirani Elixir, Goregaon West
- Axiom Rudra, Goregaon West
- Ashirwad Avenue, Goregaon West
- Ekta Suprabhat C.H.S.L, Goregaon West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| 38 Avenue | March 2025 | January 2029 | 6% | 28 units booked out of 72 units for sale |
| Hirani Elixir | July 2025 | March 2028 | 100% | 14 units booked out of 26 units for sale |
| Axiom Rudra | July 2025 | March 2030 | 25% | 30 units booked out of 98 units for sale |
| Ashirwad Avenue | January 2025 | December 2028 | 100% | 51 units booked out of 78 units for sale |
| Ekta Suprabhat C.H.S.L | November 2024 | December 2025 | 100% | – |
About this project
Ariha Skyes by Ariha Globe LLP is an 88-unit SRA-sanctioned project in Goregaon West, Mumbai 400104, launched in May 2025 with possession due in March 2029. 32 units booked out of 42 units for sale. The concrete structure (RCC) is 51% complete.
Read full summary
Ariha Skyes is an SRA-sanctioned project by Ariha Globe LLP in Goregaon West, Mumbai 400104, registered with MahaRERA as PM1180002500057. It was launched in May 2025. It has 88 units in 1 building: 77 homes (1, 2, 3 and 4 BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 88 units, 42 are for sale and 46 are rehab units for existing members.
Its registered possession date is March 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 51% complete, final finishes not started.
32 units booked out of 42 units for sale (76%). Since the July 2026 update, 10 more units have been booked and the reported concrete structure (RCC) has gone from 38% to 51%.
Ariha's track record in Mumbai
MahaRERA projects registered 2024–2026 in Mumbai
| Projects registered with MahaRERA | 4 |
|---|---|
| Total units across these projects | 1,171 |
| Completed without extending the possession date | 0 |
| Completed after an extension | 0 |
| Lapsed | 0 |
| Under construction | 4 |
| Possession date extended on the builder's application | 0 |
| MahaRERA complaints (filed by or against the builder), all Ariha projects | 0 (0 of 4 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.