Pradhan Chsl (Om Sumukha), Mulund West

by Sumukha Ventures LLP · Mulund West, Mumbai 400080 · Map

Launched
Jul 20251 yr 10 mths promised
Possession (MahaRERA)
May 2027Not extended
Concrete structure
0%Early stage
Booked (free sale)
0 of 110% · 14 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 11 units

Rehab14 units for existing members

Total 25 units. Rehab units are not for sale.

Project facts

1 BHK
6
2 BHK
13
3 BHK
6
Total units
25
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
11
Rehab units
14

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation0%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Work not started as of Oct 2026

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%0
0%0%0%0
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400080

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400080
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 10 mths2 yrs 10 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)May 2027May 2028
Concrete structure (RCC)0%45%
Units booked (free sale)0%21%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Pradhan Chsl (Om Sumukha) by Sumukha Ventures LLP is a 25-unit BMC-sanctioned project in Mulund West, Mumbai 400080, launched in July 2025 with possession due in May 2027. 0 units booked out of 11 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Pradhan Chsl (Om Sumukha) is a BMC-sanctioned project by Sumukha Ventures LLP in Mulund West, Mumbai 400080, registered with MahaRERA as PR1180002500240. It was launched in July 2025. It has 25 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 25 units, 11 are for sale and 14 are rehab units for existing members.

Its registered possession date is May 2027, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started.

0 units booked out of 11 units for sale (0%).