Ruparel Arista, Mulund West
by R R Builders · Mulund West, Mumbai 400080 · Map
- Launched
- Aug 20252 yrs 7 mths promised
- Possession (MahaRERA)
- Mar 2028Not extended
- Concrete structure
- 35%Mid-construction
- Booked (free sale)
- 10 of 1759% · 12 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale10 booked out of 17 units
Rehab12 units for existing members
Total 29 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 14
- 3 BHK
- 12
- Other units
- 3
- Total units
- 29
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 17
- Rehab units
- 12
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 35% | 0% | 10 | |
| 100% | 20% | 0% | 10 | |
| 100% | 0% | 0% | 2 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400080
Projects with 10–60 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 7 mths | 2 yrs 10 mths |
| Possession date extended | No | 1 of 6 |
| Possession date (MahaRERA) | Mar 2028 | Sep 2028 |
| Concrete structure (RCC) | 35% | 22% |
| Units booked (free sale) | 59% | 28% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Horizon Nitya, Mulund West
- Nahur Villa Cottage CHSL, Mulund West
- Pradhan Chsl (Om Sumukha), Mulund West
- Anand One, Mulund West
- Stellar, Mulund West
- Borana Business Centre, Mulund West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Horizon Nitya | August 2025 | June 2028 | 100% | 3 units booked out of 12 units for sale |
| Nahur Villa Cottage CHSL | August 2025 | May 2028 | 56% | 7 units booked out of 23 units for sale |
| Pradhan Chsl (Om Sumukha) | July 2025 | May 2027 | 0% | 0 units booked out of 11 units for sale |
| Anand One | September 2025 | December 2030 | 20% | 9 units booked out of 16 units for sale |
| Stellar | July 2025 | December 2028 | 0% | 0 units booked out of 9 units for sale |
| Borana Business Centre | September 2025 | January 2030 | 24% | 37 units booked out of 66 units for sale |
About this project
Ruparel Arista by R R Builders (Ruparel) is a 29-unit SRA-sanctioned project in Mulund West, Mumbai 400080, launched in August 2025 with possession due in March 2028. 10 units booked out of 17 units for sale. The concrete structure (RCC) is 35% complete.
Read full summary
Ruparel Arista is an SRA-sanctioned project by R R Builders in Mulund West, Mumbai 400080, registered with MahaRERA as PR1180002500544. It was launched in August 2025. It has 29 units in 1 building: 26 homes (2 and 3 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 29 units, 17 are for sale and 12 are rehab units for existing members.
Its registered possession date is March 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 35% complete, final finishes not started.
10 units booked out of 17 units for sale (59%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 20% to 35%.
Ruparel's track record in Mumbai
MahaRERA projects registered 2017–2025 in Mumbai
| Projects registered with MahaRERA | 28 |
|---|---|
| Total units across these projects | 6,570 |
| Completed without extending the possession date | 0 |
| Completed after an extension | 1 |
| Lapsed | 12 |
| Under construction | 15 |
| Possession date extended on the builder's application | 14 |
| Typical time from launch to 100% structure | 5 years 9 months |
| MahaRERA complaints (filed by or against the builder), all Ruparel projects | 872 (22 of 28 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.