Mairav Jayesh, Ghatkopar East
by Krypton Buildtech LLP · Ghatkopar East, Mumbai 400077 · Map
- Launched
- Aug 20253 yrs 3 mths promised
- Possession (MahaRERA)
- Nov 2028Not extended
- Concrete structure
- 30%Mid-construction
- Booked (free sale)
- 1 of 1010% · 32 rehab units
- Buildings
- 20.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale1 booked out of 10 units
Rehab32 units for existing members
Total 42 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 30
- 3 BHK
- 12
- Total units
- 42
- Buildings
- 2
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 10
- Rehab units
- 32
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 30% | 0% | 1 | |
| 100% | 0% | 0% | 1 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400077
Projects with 20–90 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 3 mths | 3 yrs 4 mths |
| Possession date extended | No | 0 of 4 |
| Possession date (MahaRERA) | Nov 2028 | Sep 2028 |
| Concrete structure (RCC) | 30% | 25% |
| Units booked (free sale) | 10% | 23% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Shree Matru Krupa, Ghatkopar East
- The Mansion, Ghatkopar East
- JVM's Shanay Vista, Ghatkopar East
- Rajshree Aranya, Ghatkopar East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shree Matru Krupa | August 2025 | March 2028 | 30% | 1 unit booked out of 18 units for sale |
| The Mansion | June 2025 | September 2028 | 70% | 6 units booked out of 21 units for sale |
| JVM's Shanay Vista | June 2025 | October 2028 | 0% | 3 units booked out of 16 units for sale |
| Rajshree Aranya | February 2026 | December 2029 | 20% | 4 units booked out of 15 units for sale |
About this project
Mairav Jayesh by Krypton Buildtech LLP is a 42-unit BMC-sanctioned project in Ghatkopar East, Mumbai 400077, launched in August 2025 with possession due in November 2028. 1 unit booked out of 10 units for sale. The concrete structure (RCC) is 30% complete.
Read full summary
Mairav Jayesh is a BMC-sanctioned project by Krypton Buildtech LLP in Ghatkopar East, Mumbai 400077, registered with MahaRERA as PR1180002500531. It was launched in August 2025. It has 42 units in 2 buildings, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 42 units, 10 are for sale and 32 are rehab units for existing members.
Its registered possession date is November 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 30% complete, final finishes not started.
1 unit booked out of 10 units for sale (10%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 30%.