The Mansion, Ghatkopar East
by Dhirajlal Kamdar · Ghatkopar East, Mumbai 400077 · Map
- Launched
- Jun 20253 yrs 3 mths promised
- Possession (MahaRERA)
- Sep 2028Not extended
- Concrete structure
- 70%Mid-construction
- Booked (free sale)
- 6 of 2129% · 18 rehab units
- Buildings
- 10.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale6 booked out of 21 units
Rehab18 units for existing members
Total 39 units. Rehab units are not for sale.
Project facts
- 3 BHK
- 22
- 4 BHK
- 17
- Total units
- 39
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 21
- Rehab units
- 18
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 70% | 0% | 6 | |
| 100% | 70% | 0% | 6 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400077
Projects with 10–80 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 3 mths | 2 yrs 6 mths |
| Possession date extended | No | 0 of 6 |
| Possession date (MahaRERA) | Sep 2028 | Jan 2028 |
| Concrete structure (RCC) | 70% | 55% |
| Units booked (free sale) | 29% | 14% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- JVM's Shanay Vista, Ghatkopar East
- Mairav Jayesh, Ghatkopar East
- Shree Matru Krupa, Ghatkopar East
- Urban Frames, Ghatkopar East
- Garden Palacio, Ghatkopar East
- Vardhaman Aarambh, Ghatkopar East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| JVM's Shanay Vista | June 2025 | October 2028 | 0% | 3 units booked out of 16 units for sale |
| Mairav Jayesh | August 2025 | November 2028 | 30% | 1 unit booked out of 10 units for sale |
| Shree Matru Krupa | August 2025 | March 2028 | 30% | 1 unit booked out of 18 units for sale |
| Urban Frames | April 2025 | October 2027 | 92% | 1 unit booked out of 21 units for sale |
| Garden Palacio | August 2025 | December 2027 | 100% | 3 units booked out of 9 units for sale |
| Vardhaman Aarambh | August 2025 | December 2027 | 80% | 4 units booked out of 4 units for sale |
About this project
The Mansion by Dhirajlal Kamdar is a 39-unit BMC-sanctioned project in Ghatkopar East, Mumbai 400077, launched in June 2025 with possession due in September 2028. 6 units booked out of 21 units for sale. The concrete structure (RCC) is 70% complete.
Read full summary
The Mansion is a BMC-sanctioned project by Dhirajlal Kamdar in Ghatkopar East, Mumbai 400077, registered with MahaRERA as P51800080426. It was launched in June 2025. It has 39 units in 1 building, with 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 39 units, 21 are for sale and 18 are rehab units for existing members.
Its registered possession date is September 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 70% complete, final finishes not started.
6 units booked out of 21 units for sale (29%).