Platinum Square, Kurla West

by N I Enterprises · Kurla West, Mumbai 400070 · Map

Launched
Sep 20252 yrs 3 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
60%Mid-construction
Booked (free sale)
4 of 1527%
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale4 booked out of 15 units

Land-owner share8 units, not for sale

Total 23 units. Land-owner units are not for sale.

Project facts

1 BHK
22
Other units
1
Total units
23
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
15
Land-owner share (not for sale)
8

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)60%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 20%Jul 2026: Concrete structure (RCC) 60%Oct 2026: Concrete structure (RCC) 60%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 60%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%60%0%4
100%60%0%2
100%20%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400070

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400070
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 3 mths2 yrs 9 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Dec 2027Dec 2027
Concrete structure (RCC)60%0%
Units booked (free sale)27%30%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Platinum Square by N I Enterprises is a 23-unit BMC-sanctioned project in Kurla West, Mumbai 400070, launched in September 2025 with possession due in December 2027. 4 units booked out of 15 units for sale. The concrete structure (RCC) is 60% complete.

Read full summary

Platinum Square is a BMC-sanctioned project by N I Enterprises in Kurla West, Mumbai 400070, registered with MahaRERA as PR1180002500960. It was launched in September 2025. It has 23 units in 1 building: 22 homes (1 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 23 units, 15 are for sale and 8 are the land-owner's share, not for sale.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 60% complete, final finishes not started.

4 units booked out of 15 units for sale (27%). Since the July 2026 update, 2 more units have been booked.