Skip to main content

Majestic Vista, Kurla West

by Majestic Royale Vismit Infraventures LLP · Kurla West, Mumbai 400070 · Map

Launched
Mar 20253 yrs 3 mths promised
Possession (MahaRERA)
Jun 2028Not extended
Concrete structure
90%Mid-construction
Booked (free sale)
8 of 2236% · 22 rehab units
Buildings
20.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale8 booked out of 22 units

Rehab22 units for existing members

Total 44 units. Rehab units are not for sale.

Project facts

1 BHK
15
2 BHK
19
3 BHK
10
Total units
44
Buildings
2
Land
0.5 acres
Phases
1
MahaRERA complaints
0
Free-sale units
22
Rehab units
22

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)90%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 60%Oct 2026: Concrete structure (RCC) 90%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 90%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%90%0%8
100%60%0%3
100%0%0%3

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400070

Projects with 20–90 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400070
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 3 mths2 yrs 9 mths
Possession date extendedNo0 of 5
Possession date (MahaRERA)Jun 2028Dec 2027
Concrete structure (RCC)90%60%
Units booked (free sale)36%30%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Majestic Vista by Majestic Royale Vismit Infraventures LLP is a 44-unit BMC-sanctioned project in Kurla West, Mumbai 400070, launched in March 2025 with possession due in June 2028. 8 units booked out of 22 units for sale. The concrete structure (RCC) is 90% complete.

Read full summary

Majestic Vista is a BMC-sanctioned project by Majestic Royale Vismit Infraventures LLP in Kurla West, Mumbai 400070, registered with MahaRERA as P51800079754. It was launched in March 2025. It has 44 units in 2 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 44 units, 22 are for sale and 22 are rehab units for existing members.

Its registered possession date is June 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 90% complete, final finishes not started.

8 units booked out of 22 units for sale (36%). Since the July 2026 update, 5 more units have been booked and the reported concrete structure (RCC) has gone from 60% to 90%.