Madhusudan Shrine, Malad West

by Madhusudan Developers · Malad West, Mumbai 400064 · Map

Launched
Oct 20253 yrs 5 mths promised
Possession (MahaRERA)
Mar 2029Not extended
Concrete structure
33%Mid-construction
Booked (free sale)
0 of 30% · 9 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 3 units

Rehab9 units for existing members

Total 12 units. Rehab units are not for sale.

Project facts

1 BHK
3
2 BHK
9
Total units
12
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
3
Rehab units
9

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)33%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 10%Oct 2026: Concrete structure (RCC) 33%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 33%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%33%0%0
100%10%0%0
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400064

Projects with up to 30 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400064
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 5 mths3 yrs 4 mths
Possession date extendedNo0 of 5
Possession date (MahaRERA)Mar 2029Dec 2028
Concrete structure (RCC)33%20%
Units booked (free sale)0%0%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Madhusudan Shrine by Madhusudan Developers is a 12-unit BMC-sanctioned project in Malad West, Mumbai 400064, launched in October 2025 with possession due in March 2029. 0 units booked out of 3 units for sale. The concrete structure (RCC) is 33% complete.

Read full summary

Madhusudan Shrine is a BMC-sanctioned project by Madhusudan Developers in Malad West, Mumbai 400064, registered with MahaRERA as PR1180002501307. It was launched in October 2025. It has 12 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 12 units, 3 are for sale and 9 are rehab units for existing members.

Its registered possession date is March 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 33% complete, final finishes not started.

0 units booked out of 3 units for sale (0%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 10% to 33%.