The Redevelopment Of Joe Henriques Bungalow, Malad West

by Pranav Constructions Limited · Malad West, Mumbai 400064 · Map

Launched
Dec 20252 yrs 11 mths promised
Possession (MahaRERA)
Nov 2028Not extended
Concrete structure
0%Early stage
Booked (free sale)
6 of 1155%
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale6 booked out of 11 units

Land-owner share4 units, not for sale

Total 15 units. Land-owner units are not for sale.

Project facts

1 BHK
2
2 BHK
9
3 BHK
4
Total units
15
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0
Free-sale units
11
Land-owner share (not for sale)
4

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 50%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%6
50%0%0%4
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400064

Projects with up to 30 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400064
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 11 mths3 yrs 4 mths
Possession date extendedNo0 of 5
Possession date (MahaRERA)Nov 2028Dec 2028
Concrete structure (RCC)0%33%
Units booked (free sale)55%0%
MahaRERA complaints (filed by or against the builder)00

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

The Redevelopment Of Joe Henriques Bungalow by Pranav Constructions Limited is a 15-unit BMC-sanctioned project in Malad West, Mumbai 400064, launched in December 2025 with possession due in November 2028. 6 units booked out of 11 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

The Redevelopment Of Joe Henriques Bungalow is a BMC-sanctioned project by Pranav Constructions Limited in Malad West, Mumbai 400064, registered with MahaRERA as PR1180002501744. It was launched in December 2025. It has 15 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 15 units, 11 are for sale and 4 are the land-owner's share, not for sale.

Its registered possession date is November 2028, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

6 units booked out of 11 units for sale (55%). Since the July 2026 update, 2 more units have been booked.

Pranav's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA47
Total units across these projects2,365
Completed without extending the possession date24
Completed after an extension0
Lapsed0
Under construction23
Possession date extended on the builder's application0
Typical time from launch to 100% structure2 years 10 months
MahaRERA complaints (filed by or against the builder), all Pranav projects4 (4 of 47 projects)