Skip to main content

Deep Shikhar, Malad West

by Shree Ram Krushna Spaces LLP · Malad West, Mumbai 400064 · Map

Launched
Nov 20253 yrs 4 mths promised
Possession (MahaRERA)
Mar 2029Not extended
Concrete structure
27%Mid-construction
Booked (free sale)
14 of 1974% · 48 rehab units
Buildings
10.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale14 booked out of 19 units

Rehab48 units for existing members

Total 67 units. Rehab units are not for sale.

Project facts

2 BHK
56
3 BHK
11
Total units
67
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
0
Free-sale units
19
Rehab units
48

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)27%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 10%Oct 2026: Concrete structure (RCC) 27%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 27%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%27%0%14
100%10%0%14
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400064

Projects with 30–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400064
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 4 mths2 yrs 11 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Mar 2029Oct 2028
Concrete structure (RCC)27%31%
Units booked (free sale)74%14%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Deep Shikhar by Shree Ram Krushna Spaces LLP is a 67-unit BMC-sanctioned project in Malad West, Mumbai 400064, launched in November 2025 with possession due in March 2029. 14 units booked out of 19 units for sale. The concrete structure (RCC) is 27% complete.

Read full summary

Deep Shikhar is a BMC-sanctioned project by Shree Ram Krushna Spaces LLP in Malad West, Mumbai 400064, registered with MahaRERA as PR1180002501464. It was launched in November 2025. It has 67 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 67 units, 19 are for sale and 48 are rehab units for existing members.

Its registered possession date is March 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 27% complete, final finishes not started.

14 units booked out of 19 units for sale (74%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 10% to 27%.