Skip to main content

Jdn Cornerstone, Malad West

by Jdn Builders LLP · Malad West, Mumbai 400064 · Map

Launched
Dec 20254 yrs promised
Possession (MahaRERA)
Dec 2029Not extended
Concrete structure
10%Mid-construction
Booked (free sale)
3 of 457% · 74 rehab units
Buildings
10.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale3 booked out of 45 units

Rehab74 units for existing members

Total 119 units. Rehab units are not for sale.

Project facts

1 BHK
45
2 BHK
46
Other units
28
Total units
119
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
0
Free-sale units
45
Rehab units
74

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)10%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 80%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 10%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 10%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%10%0%3
80%0%0%0
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400064

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400064
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs3 yrs 3 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)Dec 2029Jan 2029
Concrete structure (RCC)10%38%
Units booked (free sale)7%23%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Jdn Cornerstone by Jdn Builders LLP is a 119-unit BMC-sanctioned project in Malad West, Mumbai 400064, launched in December 2025 with possession due in December 2029. 3 units booked out of 45 units for sale. The concrete structure (RCC) is 10% complete.

Read full summary

Jdn Cornerstone is a BMC-sanctioned project by Jdn Builders LLP in Malad West, Mumbai 400064, registered with MahaRERA as PM1180002501909. It was launched in December 2025. It has 119 units in 1 building: 91 homes (1 and 2 BHK) and 28 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 119 units, 45 are for sale and 74 are rehab units for existing members.

Its registered possession date is December 2029, unchanged since launch. Construction: excavation complete, structure (RCC) 10% complete, final finishes not started.

3 units booked out of 45 units for sale (7%). Since the July 2026 update, 3 more units have been booked and the reported concrete structure (RCC) has gone from 0% to 10%.