Skip to main content

Rajal Dhanlaxmi, Ghatkopar West

by Nisar Properties Pvt Ltd · Ghatkopar West, Mumbai 400086 · Map

Launched
Nov 20253 yrs 1 mth promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
3 of 1323% · 14 rehab units
Buildings
20.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale3 booked out of 13 units

Rehab14 units for existing members

Total 27 units. Rehab units are not for sale.

Project facts

1 BHK
10
2 BHK
16
3 BHK
1
Total units
27
Buildings
2
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
13
Rehab units
14

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2025Jul 2026Oct 2026Dec 2025: Excavation 0%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 60%Oct 2026: Concrete structure (RCC) 100%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%3
100%60%0%1
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400086

Projects with 10–60 flats, launched within 1 year of this one.

Compared with 4 similar projects in PIN 400086
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 1 mth3 yrs 2 mths
Possession date extendedNo1 of 4
Possession date (MahaRERA)Dec 2028Jun 2029
Concrete structure (RCC)100%0%
Units booked (free sale)23%0%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Rajal Dhanlaxmi by Nisar Properties Pvt Ltd is a 27-unit BMC-sanctioned project in Ghatkopar West, Mumbai 400086, launched in November 2025 with possession due in December 2028. 3 units booked out of 13 units for sale. The concrete structure (RCC) is complete.

Read full summary

Rajal Dhanlaxmi is a BMC-sanctioned project by Nisar Properties Pvt Ltd in Ghatkopar West, Mumbai 400086, registered with MahaRERA as PR1180002501553. It was launched in November 2025. It has 27 units in 2 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 27 units, 13 are for sale and 14 are rehab units for existing members.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes not started.

3 units booked out of 13 units for sale (23%). Since the July 2026 update, 2 more units have been booked and the reported concrete structure (RCC) has gone from 60% to 100%.