Arihant Neminath Sky, Ghatkopar West
by S. P. Infra · Ghatkopar West, Mumbai 400086 · Map
- Launched
- Sep 20253 yrs 3 mths promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 0 of 300% · 20 rehab units
- Buildings
- 20.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale0 booked out of 30 units
Rehab20 units for existing members
Total 50 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 3
- 2 BHK
- 34
- 3 BHK
- 13
- Total units
- 50
- Buildings
- 2
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 30
- Rehab units
- 20
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 75% | 0% | 0% | 0 | |
| 75% | 0% | 0% | 0 | |
| 0% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400086
Projects with 20–100 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 3 mths | 3 yrs 1 mth |
| Possession date extended | No | 1 of 6 |
| Possession date (MahaRERA) | Dec 2028 | Dec 2028 |
| Concrete structure (RCC) | 0% | 45% |
| Units booked (free sale) | 0% | 13% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Swastik Prabhasa, Ghatkopar West
- Rajal Dhanlaxmi, Ghatkopar West
- Kadri Residency B Wing, Ghatkopar West
- Crystal Pearl, Ghatkopar West
- Patel Bhuvan, Ghatkopar West
- Kesar Leor, Ghatkopar West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Swastik Prabhasa | November 2025 | December 2028 | 0% | 1 unit booked out of 32 units for sale |
| Rajal Dhanlaxmi | November 2025 | December 2028 | 100% | 3 units booked out of 13 units for sale |
| Kadri Residency B Wing | February 2025 | December 2027 | 90% | – |
| Crystal Pearl | January 2025 | December 2030 | 0% | 1 unit booked out of 68 units for sale |
| Patel Bhuvan | November 2024 | December 2028 | 0% | – |
| Kesar Leor | November 2024 | August 2026 | 100% | 15 units booked out of total 33 units |
About this project
Arihant Neminath Sky by S. P. Infra is a 50-unit BMC-sanctioned project in Ghatkopar West, Mumbai 400086, launched in September 2025 with possession due in December 2028. 0 units booked out of 30 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Arihant Neminath Sky is a BMC-sanctioned project by S. P. Infra in Ghatkopar West, Mumbai 400086, registered with MahaRERA as PR1180002500708. It was launched in September 2025. It has 50 units in 2 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 50 units, 30 are for sale and 20 are rehab units for existing members.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation 75% complete, structure (RCC) not started, final finishes not started.
0 units booked out of 30 units for sale (0%).