Truvy Signature, Mulund East
by Truvy Infras LLP · Mulund East, Mumbai 400081 · Map
- Launched
- Jan 20261 yr 11 mths promised
- Possession (MahaRERA)
- Dec 2027Not extended
- Concrete structure
- 77%Mid-construction
- Booked (free sale)
- 3 of 1520% · 20 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale3 booked out of 15 units
Rehab20 units for existing members
Total 35 units. Rehab units are not for sale.
Project facts
- 1 RK
- 4
- 1 BHK
- 10
- 2 BHK
- 15
- 3 BHK
- 6
- Total units
- 35
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 15
- Rehab units
- 20
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 77% | 0% | 3 | |
| 100% | 0% | 0% | 3 | |
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400081
Projects with 10–70 flats, launched within 1 year of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 1 yr 11 mths | 3 yrs 8 mths |
| Possession date extended | No | 0 of 4 |
| Possession date (MahaRERA) | Dec 2027 | Dec 2029 |
| Concrete structure (RCC) | 77% | 2% |
| Units booked (free sale) | 20% | 32% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Yugant, Mulund East
- Signature Residences By C.K.V, Mulund East
- HS Crest, Mulund East
- New Usha Vihar Chsl, Mulund East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Yugant | December 2025 | June 2029 | 10% | 6 units booked out of 22 units for sale |
| Signature Residences By C.K.V | September 2025 | December 2031 | 5% | 30 units booked out of total 82 units |
| HS Crest | June 2026 | April 2030 | 0% | 0 units booked out of 43 units for sale |
| New Usha Vihar Chsl | September 2026 | August 2029 | 0% | 15 units booked out of 25 units for sale |
About this project
Truvy Signature by Truvy Infras LLP is a 35-unit BMC-sanctioned project in Mulund East, Mumbai 400081, launched in January 2026 with possession due in December 2027. 3 units booked out of 15 units for sale. The concrete structure (RCC) is 77% complete.
Read full summary
Truvy Signature is a BMC-sanctioned project by Truvy Infras LLP in Mulund East, Mumbai 400081, registered with MahaRERA as PR1180002501988. It was launched in January 2026. It has 35 units in 1 building, with 1 RK, 1 BHK, 2 BHK and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 35 units, 15 are for sale and 20 are rehab units for existing members.
Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) 77% complete, final finishes not started.
3 units booked out of 15 units for sale (20%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 77%.