Skip to main content

Platinum Classic, Andheri West

by Platinumcorp Urban Developers LLP · Andheri West, Mumbai 400053 · Map

Launched
Jan 20263 yrs 5 mths promised
Possession (MahaRERA)
Jun 2029Not extended
Concrete structure
0%Early stage
Booked (free sale)
28 of 8035% · 80 rehab units
Buildings
20.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale28 booked out of 80 units

Rehab80 units for existing members

Total 160 units. Rehab units are not for sale.

Project facts

1 BHK
146
2 BHK
14
Total units
160
Buildings
2
Land
0.5 acres
Phases
1
MahaRERA complaints
0
Free-sale units
80
Rehab units
80

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation50%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 35%Oct 2026: Excavation 50%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 50%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
50%0%0%28
35%0%0%13

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400053

Projects with 80–350 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400053
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 5 mths3 yrs 9 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Jun 2029Dec 2029
Concrete structure (RCC)0%0%
Units booked (free sale)35%43%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Platinum Classic by Platinumcorp Urban Developers LLP is a 160-unit MHADA-sanctioned project in Andheri West, Mumbai 400053, launched in January 2026 with possession due in June 2029. 28 units booked out of 80 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Platinum Classic is a MHADA-sanctioned project by Platinumcorp Urban Developers LLP in Andheri West, Mumbai 400053, registered with MahaRERA as PR1180002502056. It was launched in January 2026. It has 160 units in 2 buildings, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 160 units, 80 are for sale and 80 are rehab units for existing members.

Its registered possession date is June 2029, unchanged since launch. Construction: excavation 50% complete, structure (RCC) not started, final finishes not started.

28 units booked out of 80 units for sale (35%). Since the July 2026 update, 15 more units have been booked.