Serenova, Andheri West

by Kolte-Patil Developers Limited · Andheri West, Mumbai 400053 · Map

Launched
Sep 20253 yrs 8 mths promised
Possession (MahaRERA)
May 2029Not extended
Concrete structure
0%Early stage
Booked (free sale)
13 of 3043% · 81 rehab units
Buildings
20.8 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale13 booked out of 30 units

Rehab81 units for existing members

Total 111 units. Rehab units are not for sale.

Project facts

1 BHK
14
2 BHK
82
3 BHK
15
Total units
111
Buildings
2
Land
0.8 acres
Phases
1
MahaRERA complaints
0
Free-sale units
30
Rehab units
81

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation0%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Work not started as of Oct 2026

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%13
0%0%0%13
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400053

Projects with 50–250 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400053
MeasureThis projectSimilar projects
Launch to possession (as first promised)3 yrs 8 mths3 yrs 8 mths
Possession date extendedNo0 of 6
Possession date (MahaRERA)May 2029Jun 2029
Concrete structure (RCC)0%4%
Units booked (free sale)43%21%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Serenova by Kolte-Patil Developers Limited is a 111-unit BMC-sanctioned project in Andheri West, Mumbai 400053, launched in September 2025 with possession due in May 2029. 13 units booked out of 30 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Serenova is a BMC-sanctioned project by Kolte-Patil Developers Limited in Andheri West, Mumbai 400053, registered with MahaRERA as PR1180002500850. It was launched in September 2025. It has 111 units in 2 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 111 units, 30 are for sale and 81 are rehab units for existing members.

Its registered possession date is May 2029, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started.

13 units booked out of 30 units for sale (43%).