Skip to main content

Pearl Solitaire, Malad East

by Pearl Infra · Malad East, Mumbai 400097 · Map

Launched
Jan 20264 yrs 11 mths promised
Possession (MahaRERA)
Dec 2030Not extended
Concrete structure
0%Early stage
Booked (free sale)
0 of 220% · 36 rehab units
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 22 units

Rehab36 units for existing members

Total 58 units. Rehab units are not for sale.

Project facts

1 BHK
15
2 BHK
38
3 BHK
5
Total units
58
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
22
Rehab units
36

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 90%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 0%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%0%0
90%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400097

Projects with 20–150 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400097
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 11 mths2 yrs 10 mths
Possession date extendedNo0 of 4
Possession date (MahaRERA)Dec 2030Jul 2028
Concrete structure (RCC)0%34%
Units booked (free sale)0%12%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Pearl Solitaire by Pearl Infra is a 58-unit BMC-sanctioned project in Malad East, Mumbai 400097, launched in January 2026 with possession due in December 2030. 0 units booked out of 22 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Pearl Solitaire is a BMC-sanctioned project by Pearl Infra in Malad East, Mumbai 400097, registered with MahaRERA as PR1180002502107. It was launched in January 2026. It has 58 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 58 units, 22 are for sale and 36 are rehab units for existing members.

Its registered possession date is December 2030, unchanged since launch. Construction: excavation complete, structure (RCC) not started, final finishes not started.

0 units booked out of 22 units for sale (0%).