Nirmal Bhavan Chsl, Vile Parle West
by Pranav Constructions Limited · Vile Parle West, Mumbai 400056 · Map
- Launched
- Feb 20262 yrs 10 mths promised
- Possession (MahaRERA)
- Dec 2028Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 10 of 2148% · 12 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale10 booked out of 21 units
Rehab12 units for existing members
Total 33 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 14
- 2 BHK
- 16
- 3 BHK
- 3
- Total units
- 33
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 21
- Rehab units
- 12
- Reserved units
- 10
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 75% | 0% | 0% | 10 | |
| 0% | 0% | 0% | 10 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400056
Projects with 10–70 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 10 mths | 3 yrs 2 mths |
| Possession date extended | No | 1 of 4 |
| Possession date (MahaRERA) | Dec 2028 | Jun 2029 |
| Concrete structure (RCC) | 0% | 14% |
| Units booked (free sale) | 48% | 12% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- SM Sonali, Vile Parle West
- Radha Madhuban, Vile Parle West
- Varsha, Vile Parle West
- The Alka Co-Operative Housing Society Limited, Vile Parle West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| SM Sonali | March 2026 | December 2028 | 27% | 3 units booked out of 13 units for sale |
| Radha Madhuban | June 2026 | December 2029 | 0% | 0 units booked out of 18 units for sale |
| Varsha | July 2026 | April 2031 | 0% | 13 units booked out of 26 units for sale |
| The Alka Co-Operative Housing Society Limited | August 2025 | April 2027 | 60% | 0 units booked out of 10 units for sale |
About this project
Nirmal Bhavan Chsl by Pranav Constructions Limited is a 33-unit SRA-sanctioned project in Vile Parle West, Mumbai 400056, launched in February 2026 with possession due in December 2028. 10 units booked out of 21 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Nirmal Bhavan Chsl is an SRA-sanctioned project by Pranav Constructions Limited in Vile Parle West, Mumbai 400056, registered with MahaRERA as PR1180002502406. It was launched in February 2026. It has 33 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 33 units, 21 are for sale and 12 are rehab units for existing members.
Its registered possession date is December 2028, unchanged since launch. Construction: excavation 75% complete, structure (RCC) not started, final finishes not started.
10 units booked out of 21 units for sale (48%).
Pranav's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 47 |
|---|---|
| Total units across these projects | 2,365 |
| Completed without extending the possession date | 24 |
| Completed after an extension | 0 |
| Lapsed | 0 |
| Under construction | 23 |
| Possession date extended on the builder's application | 0 |
| Typical time from launch to 100% structure | 2 years 10 months |
| MahaRERA complaints (filed by or against the builder), all Pranav projects | 4 (4 of 47 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.