Varsha, Vile Parle West
by Omshreemahavir Developers Private Limited · Vile Parle West, Mumbai 400056 · Map
- Launched
- Jul 20264 yrs 5 mths originally promised
- Possession (MahaRERA)
- Apr 2031Extended by 4 mths
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 13 of 2650% · 14 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale13 booked out of 26 units
Rehab14 units for existing members
Land-owner share1 unit, not for sale
Total 41 units. Rehab and land-owner units are not for sale.
Project facts
- 1 RK
- 7
- 1 BHK
- 4
- 2 BHK
- 3
- 3 BHK
- 14
- 5+ BHK
- 1
- Other units
- 12
- Total units
- 41
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 26
- Rehab units
- 14
- Land-owner share (not for sale)
- 1
- Reserved units
- 13
Construction progress
As reported by the builder to MahaRERA (whole project)
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 13 |
"–" means MahaRERA shows no figure for that update.
Compared with 4 similar projects in PIN 400056
Projects with 10–60 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 5 mths | 2 yrs 10 mths |
| Possession date extended | By 4 mths | 0 of 4 |
| Possession date (MahaRERA) | Apr 2031 | Dec 2028 |
| Concrete structure (RCC) | 0% | 0% |
| Units booked (free sale) | 50% | 12% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 4 projects
- Radha Madhuban, Vile Parle West
- Veer Elegance, Vile Parle West
- SM Sonali, Vile Parle West
- Nirmal Bhavan Chsl, Vile Parle West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Radha Madhuban | June 2026 | December 2029 | 0% | 0 units booked out of 18 units for sale |
| Veer Elegance | September 2026 | December 2028 | 0% | 0 units booked out of 10 units for sale |
| SM Sonali | March 2026 | December 2028 | 27% | 3 units booked out of 13 units for sale |
| Nirmal Bhavan Chsl | February 2026 | December 2028 | 0% | 10 units booked out of 21 units for sale |
About this project
Varsha by Omshreemahavir Developers Private Limited is a 41-unit BMC-sanctioned project in Vile Parle West, Mumbai 400056, launched in July 2026 with possession due in April 2031. 13 units booked out of 26 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Varsha is a BMC-sanctioned project by Omshreemahavir Developers Private Limited in Vile Parle West, Mumbai 400056, registered with MahaRERA as PR1180002601329. It was launched in July 2026. It has 41 units in 1 building: 29 homes (1 RK, 1 BHK, 2 BHK, 3 BHK and 5+ BHK) and 12 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 41 units, 26 are for sale, 14 are rehab units for existing members and 1 is the land-owner's share, not for sale.
Its registered possession date is April 2031, extended by 4 months from the original December 2030. Construction: excavation complete, structure (RCC) not started, final finishes not started.
13 units booked out of 26 units for sale (50%).