Elixir One, Mulund West

by Elixir Properties LLP · Mulund West, Mumbai 400080 · Map

Launched
Feb 20262 yrs 10 mths promised
Possession (MahaRERA)
Dec 2028Not extended
Concrete structure
75%Mid-construction
Booked (free sale)
0 of 100% · 14 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 10 units

Rehab14 units for existing members

Total 24 units. Rehab units are not for sale.

Project facts

1 BHK
4
2 BHK
19
3 BHK
1
Total units
24
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
10
Rehab units
14

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)75%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 100%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 50%Oct 2026: Concrete structure (RCC) 75%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 75%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%75%0%0
100%50%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400080

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400080
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 10 mths2 yrs 8 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)Dec 2028Sep 2028
Concrete structure (RCC)75%32%
Units booked (free sale)0%8%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Elixir One by Elixir Properties LLP is a 24-unit BMC-sanctioned project in Mulund West, Mumbai 400080, launched in February 2026 with possession due in December 2028. 0 units booked out of 10 units for sale. The concrete structure (RCC) is 75% complete.

Read full summary

Elixir One is a BMC-sanctioned project by Elixir Properties LLP in Mulund West, Mumbai 400080, registered with MahaRERA as PR1180002502474. It was launched in February 2026. It has 24 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 24 units, 10 are for sale and 14 are rehab units for existing members.

Its registered possession date is December 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 75% complete, final finishes not started.

0 units booked out of 10 units for sale (0%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 50% to 75%.