Brijwasi Bliss, Mulund West

by M/s. BRIJWASI BLISS · Mulund West, Mumbai 400080 · Map

Launched
Feb 20261 yr 10 mths promised
Possession (MahaRERA)
Dec 2027Not extended
Concrete structure
100%Nearing possession
Booked (free sale)
1 of 138% · 14 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale1 booked out of 13 units

Rehab14 units for existing members

Total 27 units. Rehab units are not for sale.

Project facts

1 BHK
8
2 BHK
16
4 BHK
1
Other units
2
Total units
27
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
13
Rehab units
14

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services40%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 100%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Jul 2026: Final finishes 5%Oct 2026: Final finishes 40%Excavation 100%Concrete structure (RCC) 100%Final finishes 40%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%40%1
100%100%5%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400080

Projects with 10–50 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400080
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 10 mths2 yrs 9 mths
Possession date extendedNo1 of 6
Possession date (MahaRERA)Dec 2027Dec 2028
Concrete structure (RCC)100%32%
Units booked (free sale)8%8%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Brijwasi Bliss by M/s. BRIJWASI BLISS is a 27-unit BMC-sanctioned project in Mulund West, Mumbai 400080, launched in February 2026 with possession due in December 2027. 1 unit booked out of 13 units for sale. The concrete structure (RCC) is complete.

Read full summary

Brijwasi Bliss is a BMC-sanctioned project by M/s. BRIJWASI BLISS in Mulund West, Mumbai 400080, registered with MahaRERA as PR1180002502492. It was launched in February 2026. It has 27 units in 1 building: 25 homes (1, 2 and 4 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 27 units, 13 are for sale and 14 are rehab units for existing members.

Its registered possession date is December 2027, unchanged since launch. Construction: excavation complete, structure (RCC) complete, final finishes 40% complete.

1 unit booked out of 13 units for sale (8%). Since the July 2026 update, 1 more unit has been booked.