Park Horizon, Andheri West
by Shree Mahavir Estates · Andheri West, Mumbai 400053 · Map
- Launched
- Jul 20265 yrs 10 mths originally promised
- Possession (MahaRERA)
- Sep 2032Extended by 4 mths
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 2 of 229% · 40 rehab units
- Buildings
- 20.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale2 booked out of 22 units
Rehab40 units for existing members
Total 62 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 11
- 2 BHK
- 51
- Total units
- 62
- Buildings
- 2
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 22
- Rehab units
- 40
Construction progress
As reported by the builder to MahaRERA (whole project)
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 2 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400053
Projects with 30–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs 10 mths | 4 yrs 6 mths |
| Possession date extended | By 4 mths | 0 of 6 |
| Possession date (MahaRERA) | Sep 2032 | Dec 2030 |
| Concrete structure (RCC) | 0% | 0% |
| Units booked (free sale) | 9% | 27% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Mayfair Aranya, Andheri West
- Amaha Sunflower, Andheri West
- Naman Fifty Eight, Andheri West
- Fame Garden, Andheri West
- Platinum Vibe, Andheri West
- Sai Sea View, Andheri West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Mayfair Aranya | August 2026 | July 2032 | 0% | 98 units booked out of 128 units for sale |
| Amaha Sunflower | August 2026 | December 2030 | 0% | 12 units booked out of 22 units for sale |
| Naman Fifty Eight | May 2026 | March 2031 | 0% | 0 units booked out of 10 units for sale |
| Fame Garden | September 2026 | December 2030 | 0% | 0 units booked out of 3 units for sale |
| Platinum Vibe | April 2026 | December 2030 | 0% | 69 units booked out of 78 units for sale |
| Sai Sea View | October 2026 | December 2029 | 0% | 0 units booked out of 60 units for sale |
About this project
Park Horizon by Shree Mahavir Estates is a 62-unit MHADA-sanctioned project in Andheri West, Mumbai 400053, launched in July 2026 with possession due in September 2032. 2 units booked out of 22 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Park Horizon is a MHADA-sanctioned project by Shree Mahavir Estates in Andheri West, Mumbai 400053, registered with MahaRERA as PR1180002601114. It was launched in July 2026. It has 62 units in 2 buildings, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 62 units, 22 are for sale and 40 are rehab units for existing members.
Its registered possession date is September 2032, extended by 4 months from the original May 2032. Construction: excavation complete, structure (RCC) not started, final finishes not started.
2 units booked out of 22 units for sale (9%).