Amaha Sunflower, Andheri West
by Build Confia India LLP · Andheri West, Mumbai 400053 · Map
- Launched
- Aug 20264 yrs 4 mths promised
- Possession (MahaRERA)
- Dec 2030Not extended
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 12 of 2255% · 20 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale12 booked out of 22 units
Rehab20 units for existing members
Total 42 units. Rehab units are not for sale.
Project facts
- 1 RK
- 3
- 1 BHK
- 5
- 2 BHK
- 18
- 3 BHK
- 10
- Other units
- 6
- Total units
- 42
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 22
- Rehab units
- 20
- Reserved units
- 12
Construction progress
As reported by the builder to MahaRERA (whole project)
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 0% | 0% | 0% | 12 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400053
Projects with 10–80 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 4 yrs 4 mths | 4 yrs 2 mths |
| Possession date extended | No | 1 of 6 |
| Possession date (MahaRERA) | Dec 2030 | Dec 2030 |
| Concrete structure (RCC) | 0% | 0% |
| Units booked (free sale) | 55% | 35% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Mayfair Aranya, Andheri West
- Fame Garden, Andheri West
- Park Horizon, Andheri West
- Kamla Iris, Andheri West
- Evershine Apartment No. 1, Andheri West
- The Artisan Abode, Andheri West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Mayfair Aranya | August 2026 | July 2032 | 0% | 98 units booked out of 128 units for sale |
| Fame Garden | September 2026 | December 2030 | 0% | 0 units booked out of 3 units for sale |
| Park Horizon | July 2026 | September 2032 | 0% | 2 units booked out of 22 units for sale |
| Kamla Iris | June 2026 | December 2028 | 0% | 50 units booked out of 56 units for sale |
| Evershine Apartment No. 1 | October 2026 | December 2030 | 0% | 0 units booked out of 37 units for sale |
| The Artisan Abode | November 2026 | December 2029 | 0% | 34 units booked out of 55 units for sale |
About this project
Amaha Sunflower by Build Confia India LLP is a 42-unit SRA-sanctioned project in Andheri West, Mumbai 400053, launched in August 2026 with possession due in December 2030. 12 units booked out of 22 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Amaha Sunflower is an SRA-sanctioned project by Build Confia India LLP in Andheri West, Mumbai 400053, registered with MahaRERA as PR1180002601619. It was launched in August 2026. It has 42 units in 1 building: 36 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 42 units, 22 are for sale and 20 are rehab units for existing members.
Its registered possession date is December 2030, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started.
12 units booked out of 22 units for sale (55%).