Laxmi Palace CHSL, Vile Parle East
by Prime Civil Infrastructures Private Limited · Vile Parle East, Mumbai 400057 · Map
- Launched
- Jul 20262 yrs 5 mths originally promised
- Possession (MahaRERA)
- Apr 2029Extended by 4 mths
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 10 of 1856% · 13 rehab units
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale10 booked out of 18 units
Rehab13 units for existing members
Total 31 units. Rehab units are not for sale.
Project facts
- 1 RK
- 1
- 1 BHK
- 9
- 2 BHK
- 4
- 3 BHK
- 11
- 4 BHK
- 5
- Other units
- 1
- Total units
- 31
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 18
- Rehab units
- 13
Construction progress
As reported by the builder to MahaRERA (whole project)
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 50% | 0% | 0% | 10 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400057
Projects with 10–60 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 5 mths | 2 yrs 10 mths |
| Possession date extended | By 4 mths | 1 of 6 |
| Possession date (MahaRERA) | Apr 2029 | May 2029 |
| Concrete structure (RCC) | 0% | 0% |
| Units booked (free sale) | 56% | 3% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Happy Homes, Vile Parle East
- Shyam Kutir, Vile Parle East
- 64 Crest, Vile Parle East
- Oshia Residency, Vile Parle East
- Rudraksha, Vile Parle East
- The Crown, Vile Parle East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Happy Homes | July 2026 | April 2029 | 0% | 0 units booked out of 31 units for sale |
| Shyam Kutir | August 2026 | February 2028 | 0% | 1 unit booked out of 18 units for sale |
| 64 Crest | June 2026 | May 2029 | 0% | 3 units booked out of 11 units for sale |
| Oshia Residency | June 2026 | March 2029 | 13% | 0 units booked out of total 19 units |
| Rudraksha | June 2026 | September 2029 | 0% | 1 unit booked out of 7 units for sale |
| The Crown | August 2026 | September 2029 | 0% | 0 units booked out of 7 units for sale |
About this project
Laxmi Palace CHSL by Prime Civil Infrastructures Private Limited is a 31-unit BMC-sanctioned project in Vile Parle East, Mumbai 400057, launched in July 2026 with possession due in April 2029. 10 units booked out of 18 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Laxmi Palace CHSL is a BMC-sanctioned project by Prime Civil Infrastructures Private Limited in Vile Parle East, Mumbai 400057, registered with MahaRERA as PR1180002601120. It was launched in July 2026. It has 31 units in 1 building: 30 homes (1 RK, 1 BHK, 2 BHK, 3 BHK and 4 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 31 units, 18 are for sale and 13 are rehab units for existing members.
Its registered possession date is April 2029, extended by 4 months from the original December 2028. Construction: excavation 50% complete, structure (RCC) not started, final finishes not started.
10 units booked out of 18 units for sale (56%).