Happy Homes, Vile Parle East
by Ameya Vista Premier LLP · Vile Parle East, Mumbai 400057 · Map
- Launched
- Jul 20262 yrs 5 mths originally promised
- Possession (MahaRERA)
- Apr 2029Extended by 4 mths
- Concrete structure
- 0%Early stage
- Booked (free sale)
- 0 of 310% · 17 rehab units
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale0 booked out of 31 units
Rehab17 units for existing members
Total 48 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 16
- 2 BHK
- 19
- 3 BHK
- 13
- Total units
- 48
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
- Free-sale units
- 31
- Rehab units
- 17
Construction progress
As reported by the builder to MahaRERA (whole project)
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400057
Projects with 20–100 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 2 yrs 5 mths | 3 yrs 1 mth |
| Possession date extended | By 4 mths | 1 of 6 |
| Possession date (MahaRERA) | Apr 2029 | Sep 2029 |
| Concrete structure (RCC) | 0% | 0% |
| Units booked (free sale) | 0% | 16% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Laxmi Palace CHSL, Vile Parle East
- Shyam Kutir, Vile Parle East
- 64 Crest, Vile Parle East
- Munisuvrat Chhaya, Vile Parle East
- Zee Happy Veena, Vile Parle East
- Parimal, Vile Parle East
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Laxmi Palace CHSL | July 2026 | April 2029 | 0% | 10 units booked out of 18 units for sale |
| Shyam Kutir | August 2026 | February 2028 | 0% | 1 unit booked out of 18 units for sale |
| 64 Crest | June 2026 | May 2029 | 0% | 3 units booked out of 11 units for sale |
| Munisuvrat Chhaya | September 2026 | December 2029 | 0% | 48 units booked out of 64 units for sale |
| Zee Happy Veena | September 2026 | March 2031 | 0% | 1 unit booked out of 50 units for sale |
| Parimal | September 2026 | December 2030 | 0% | 0 units booked out of 9 units for sale |
About this project
Happy Homes by Ameya Vista Premier LLP is a 48-unit BMC-sanctioned project in Vile Parle East, Mumbai 400057, launched in July 2026 with possession due in April 2029. 0 units booked out of 31 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Happy Homes is a BMC-sanctioned project by Ameya Vista Premier LLP in Vile Parle East, Mumbai 400057, registered with MahaRERA as PR1180002601155. It was launched in July 2026. It has 48 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 48 units, 31 are for sale and 17 are rehab units for existing members.
Its registered possession date is April 2029, extended by 4 months from the original December 2028. Construction: excavation complete, structure (RCC) not started, final finishes not started.
0 units booked out of 31 units for sale (0%).