Dadamiya’s Man'souza Height, Kurla West

by Dadamiya Infrastructure LLP · Kurla West, Mumbai 400070 · Map

Launched
Sep 20261 yr 6 mths promised
Possession (MahaRERA)
Mar 2028Not extended
Concrete structure
54%Mid-construction
Booked (free sale)
20 of 3656% · 22 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale20 booked out of 36 units

Rehab22 units for existing members

Total 58 units. Rehab units are not for sale.

Project facts

1 BHK
33
2 BHK
20
3 BHK
4
Other units
1
Total units
58
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
36
Rehab units
22
Reserved units
20

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)54%
Finishes, lifts and services0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%54%0%20

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400070

Projects with 20–150 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400070
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 6 mths3 yrs 6 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Mar 2028Jan 2029
Concrete structure (RCC)54%18%
Units booked (free sale)56%0%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Dadamiya’s Man'souza Height by Dadamiya Infrastructure LLP is a 58-unit SRA-sanctioned project in Kurla West, Mumbai 400070, launched in September 2026 with possession due in March 2028. 20 units booked out of 36 units for sale. The concrete structure (RCC) is 54% complete.

Read full summary

Dadamiya’s Man'souza Height is an SRA-sanctioned project by Dadamiya Infrastructure LLP in Kurla West, Mumbai 400070, registered with MahaRERA as PR1180002601930. It was launched in September 2026. It has 58 units in 1 building: 57 homes (1, 2 and 3 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 58 units, 36 are for sale and 22 are rehab units for existing members.

Its registered possession date is March 2028, unchanged since launch. Construction: excavation complete, structure (RCC) 54% complete, final finishes not started.

20 units booked out of 36 units for sale (56%).