Amber Apartment, Kurla West

Lapsed

by Aman Developers · Kurla West, Mumbai 400070 · Map

Launched
Jun 2026
Possession (MahaRERA)
Feb 2026Not extendedWhat does Lapsed mean?
Concrete structure
72%Mid-construction
Booked (free sale)
0 of 110% · 33 rehab units
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 11 units

Rehab33 units for existing members

Total 44 units. Rehab units are not for sale.

Project facts

1 RK
36
Other units
8
Total units
44
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0
Free-sale units
11
Rehab units
33

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)72%
Finishes, lifts and services70%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Jul 2026Oct 2026Jul 2026: Excavation 100%Oct 2026: Excavation 100%Jul 2026: Concrete structure (RCC) 72%Oct 2026: Concrete structure (RCC) 72%Jul 2026: Final finishes 70%Oct 2026: Final finishes 70%Excavation 100%Concrete structure (RCC) 72%Final finishes 70%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%72%70%0
100%72%70%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 4 similar projects in PIN 400070

Projects with 10–80 flats, launched within 6 months of this one.

Compared with 4 similar projects in PIN 400070
MeasureThis projectSimilar projects
Possession date extendedNo0 of 4
Possession date (MahaRERA)Feb 2026Mar 2029
Concrete structure (RCC)72%9%
Units booked (free sale)0%24%
MahaRERA complaints (filed by or against the builder)00

The 4 projects

Other phases of this project are not included in the similar projects.

About this project

Amber Apartment by Aman Developers is a 44-unit BMC-sanctioned project in Kurla West, Mumbai 400070, launched in June 2026; its MahaRERA registration has lapsed. 0 units booked out of 11 units for sale. The concrete structure (RCC) is 72% complete.

Read full summary

Amber Apartment is a BMC-sanctioned project by Aman Developers in Kurla West, Mumbai 400070, registered with MahaRERA as PR1180002600756. It was launched in June 2026. It has 44 units in 1 building: 36 homes (1 RK) and 8 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 44 units, 11 are for sale and 33 are rehab units for existing members.

Possession was due in February 2026. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 72% complete, final finishes 70% complete.

0 units booked out of 11 units for sale (0%).