Intelligentia Prime by Haware Properties, Borivali East

by Haware Properties Landmarks · Borivali East, Mumbai 400066 · Map

Launched
Oct 20265 yrs 2 mths promised
Possession (MahaRERA)
Dec 2031Not extended
Concrete structure
0%Early stage
Booked (free sale)
0 of 580% · 29 rehab units
Buildings
20.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale0 booked out of 58 units

Rehab29 units for existing members

Total 87 units. Rehab units are not for sale.

Project facts

2 BHK
58
3 BHK
29
Total units
87
Buildings
2
Land
0.3 acres
Phases
1
MahaRERA complaints
0
Free-sale units
58
Rehab units
29

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation0%
Concrete structure (slabs)0%
Finishes, lifts and services0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
0%0%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400066

Projects with 40–200 flats, launched within 1 year of this one.

Compared with 3 similar projects in PIN 400066
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 2 mths3 yrs 8 mths
Possession date extendedNo0 of 3
Possession date (MahaRERA)Dec 2031Nov 2029
Concrete structure (RCC)0%0%
Units booked (free sale)0%0%
MahaRERA complaints (filed by or against the builder)00

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Intelligentia Prime by Haware Properties by Haware Properties Landmarks is an 87-unit MHADA-sanctioned project in Borivali East, Mumbai 400066, launched in October 2026 with possession due in December 2031. 0 units booked out of 58 units for sale. Work on the concrete structure (RCC) has not started.

Read full summary

Intelligentia Prime by Haware Properties is a MHADA-sanctioned project by Haware Properties Landmarks in Borivali East, Mumbai 400066, registered with MahaRERA as PR1180002602285. It was launched in October 2026. It has 87 units in 2 buildings, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active. Of the 87 units, 58 are for sale and 29 are rehab units for existing members.

Its registered possession date is December 2031, unchanged since launch. Construction: excavation not started, structure (RCC) not started, final finishes not started.

0 units booked out of 58 units for sale (0%).

Haware's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA14
Total units across these projects1,739
Completed without extending the possession date4
Completed after an extension1
Lapsed2
Under construction7
Possession date extended on the builder's application2
Typical time from launch to 100% structure5 years 8 months
MahaRERA complaints (filed by or against the builder), all Haware projects2 (2 of 14 projects)

See all Haware projects →