Mahindra Marina64, Malad West
by Mahindra Lifespace Developers limited · Malad West, Mumbai 400064 · Map
- Launched
- Jun 2025First of 3 phases
- Possession (MahaRERA)
- Dec 2029 – Jun 2030Not extended
- Concrete structure
- 0%Weighted across 3 phases
- Booked (free sale)
- 196 of 29966% · 181 rehab units
- Buildings
- 72.3 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale196 booked out of 299 units
Rehab181 units for existing members
Total 480 units. Rehab units are not for sale.
Project facts
- 2 BHK
- 198
- 3 BHK
- 211
- 4 BHK
- 29
- Other units
- 42
- Total units
- 480
- Buildings
- 7
- Land
- 2.3 acres
- Phases
- 3
- MahaRERA complaints
- 1
- Free-sale units
- 299
- Rehab units
- 181
The 3 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Mahindra Marina64 - Phase 1 Early stage | PR1181012500087 | 62 | 0% | 39% | |
| Mahindra Marina64 - Phase 2 Early stage | PR1181012500523 | 66 | 0% | 41% | |
| Mahindra Marina64 - Phase 3 Early stage | PR1182022502265 | 310 | 0% | 41% |
Show updates by phase
Mahindra Marina64 - Phase 1 (PR1181012500087)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 24 | |
| 0% | 0% | 0% | 19 | |
| 0% | 0% | 0% | 15 |
"–" means MahaRERA shows no figure for that update.
Mahindra Marina64 - Phase 2 (PR1181012500523)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 29 | |
| 0% | 0% | 0% | 27 | |
| 0% | 0% | 0% | 24 |
"–" means MahaRERA shows no figure for that update.
Mahindra Marina64 - Phase 3 (PR1182022502265)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 0% | 0% | 143 | |
| 0% | 0% | 0% | 54 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Mahindra Marina64 by Mahindra Lifespace Developers limited (Mahindra Lifespaces) is a 480-unit BMC-sanctioned project in Malad West, Mumbai 400064, registered with MahaRERA in 3 phases, with possession dates from December 2029 to June 2030. 196 units booked out of 299 units for sale. Work on the concrete structure (RCC) has not started.
Read full summary
Mahindra Marina64 is a BMC-sanctioned project by Mahindra Lifespace Developers limited in Malad West, Mumbai 400064, registered with MahaRERA as 3 phases (PR1181012500087, PR1181012500523, PR1182022502265). The first phase was launched in June 2025. Together the phases have 480 units in 7 buildings: 438 homes (2, 3 and 4 BHK) and 42 other units (shops, offices or not given by type), as registered with MahaRERA. All 3 phases are active on MahaRERA. Of the 480 units, 299 are for sale and 181 are rehab units for existing members.
The phases' registered possession dates run from December 2029 to June 2030; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 0% complete and final finishes 0% complete. None of the 3 phases has its structure complete.
196 units booked out of 299 units for sale (66%). Since the July 2026 update, 96 more units have been booked.
Mahindra Lifespaces's track record in Mumbai
MahaRERA projects registered 2017–2026 in Mumbai
| Projects registered with MahaRERA | 17 |
|---|---|
| Total units across these projects | 4,150 |
| Completed without extending the possession date | 4 |
| Completed after an extension | 2 |
| Lapsed | 3 |
| Under construction | 8 |
| Possession date extended on the builder's application | 2 |
| Typical time from launch to 100% structure | 5 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Mahindra Lifespaces projects | 4 (4 of 17 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.