Buttepatil projects in Pune
MahaRERA projects by Buttepatil registered 2017–2026 in Pune & PCMC.
| Projects registered with MahaRERA | 15 |
|---|---|
| Total units across these projects | 350 |
Full record
MahaRERA projects registered 2017–2026 in Pune & PCMC
| Completed without extending the possession date | 5 |
|---|---|
| Completed after an extension | 3 |
| Lapsed | 2 |
| Under construction | 5 |
| Possession date extended on the builder's application | 6 |
| Typical time from launch to 100% structure | 2 years 5 months |
| MahaRERA complaints (filed by or against the builder), all Buttepatil projects | 2 (2 of 15 projects) |
What these mean
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Where they build: Shivajinagar (3) · Erandwane (2) · Kothrud (1) · Warje (1) · Parvati (1)
Under construction
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| Buttepatil Capital | Shivajinagar | Mid-construction | December 2026 | 21 units booked out of total 26 units |
| Pitruchaya | Shivajinagar | Early stage | December 2029 | 13 units booked out of total 25 units |
| Serenity Residency | Parvati | Nearing possession | September 2026 | 16 units booked out of total 17 units |
| Serenity Springs | Erandwane | Ready to move | September 2026 | 17 units booked out of total 17 units |
| Sonali Society | Shivajinagar | Mid-construction | November 2027 | 6 units booked out of total 12 units |
Completed
| Project | Village | Status |
|---|---|---|
| Gulab Bhakti Niwas | Shivajinagar | Completed |
| Gulab Court | Shivajinagar | Completed |
| Gulab Heights | Erandwane | Completed |
| Gulab Kunj | Sadashiv Peth | Completed |
| Gulab Sadan | Shivajinagar | Completed |
| Gulab Shilp | Warje | Completed |
| Gulab Srushti | Kothrud | Completed |
| Gulab Vishwa | Sadashiv Peth | Completed |
Lapsed
| Project | Village | Status |
|---|---|---|
| Angelle Hills Version T | Bavdhan Khurd | Lapsed |
| Angelle Hills Version T- 9-12 Floor | Bavdhan Khurd | Lapsed |
Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.
Is a project grouped wrongly or a figure out of date? Tell us