Garve projects in Pune

MahaRERA projects by Garve registered 2017–2026 in Pune & PCMC.

Projects registered with MahaRERA16
Total units across these projects1,756
Full record

MahaRERA projects registered 2017–2026 in Pune & PCMC

Completed without extending the possession date2
Completed after an extension4
Lapsed2
Under construction8
Possession date extended on the builder's application7
Typical time from launch to 100% structure3 years 3 months
MahaRERA complaints (filed by or against the builder), all Garve projects6 (4 of 16 projects)
What these mean
  • Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
  • Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
  • Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
  • Under construction: MahaRERA status Active.
  • Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
  • Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
  • MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.

Where they build: Wakad (2) · Tathawade (2) · Pimple Gurav (2) · Punawale (1)

Under construction

ProjectVillageStagePossessionBooked
Akshara GrandeurPunawaleMid-constructionDecember 2028128 units booked out of total 437 units
Akshara MeadowsTathawadeMid-constructionDecember 202625 units booked out of total 70 units
Akshara Serenity · 2 phasesTathawadeReady to moveOct 2026 – Dec 202660 units booked out of total 80 units
Samrajya · 2 phasesPimple GuravMid-constructionDec 2028 – Dec 2031123 units booked out of total 131 units
Samrajya Wing GHPimple GuravMid-constructionDecember 2029228 units booked out of total 294 units
Completed
ProjectVillageStatus
Akshara HarmonyWakadCompleted
Akshara PlatinumWakadCompleted
Omega ParadiseWakadCompleted
SamrajyaPimple GuravCompleted
Lapsed
ProjectVillageStatus
Akshara ParkMarunjiLapsed
Omega Paradise NWakadLapsed

Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.

Is a project grouped wrongly or a figure out of date? Tell us