Gini projects in Pune
MahaRERA projects by Gini registered 2017–2024 in Pune & PCMC.
| Projects registered with MahaRERA | 13 |
|---|---|
| Total units across these projects | 2,476 |
Full record
MahaRERA projects registered 2017–2024 in Pune & PCMC
| Completed without extending the possession date | 6 |
|---|---|
| Completed after an extension | 3 |
| Lapsed | 1 |
| Under construction | 3 |
| Possession date extended on the builder's application | 3 |
| Typical time from launch to 100% structure | 2 years 9 months |
| MahaRERA complaints (filed by or against the builder), all Gini projects | 9 (3 of 13 projects) |
What these mean
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Where they build: Kiwale (2) · Yewalewadi (1)
Under construction
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| Gini Vibrance | Kiwale | Nearing possession | December 2026 | 180 units booked out of total 180 units |
| Gini Vivante · 3 phases | Kiwale | Mid-construction | Dec 2027 – Dec 2028 | 1,364 units booked out of total 1,536 units |
Completed
| Project | Village | Status |
|---|---|---|
| Bellina | Lohegaon | Completed |
| Gini Aria | Yewalewadi | Completed |
| Gini Belvista | Dhanori | Completed |
| Gini Viviana F | Baner | Completed |
Lapsed
| Project | Village | Status |
|---|---|---|
| Gini Belvista | Dhanori | Lapsed |
Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.
Is a project grouped wrongly or a figure out of date? Tell us