Gokhale Constructions projects in Pune

MahaRERA projects by Gokhale Constructions registered 2017–2026 in Pune & PCMC.

Projects registered with MahaRERA23
Total units across these projects833
Full record

MahaRERA projects registered 2017–2026 in Pune & PCMC

Completed without extending the possession date7
Completed after an extension8
Lapsed2
Under construction6
Possession date extended on the builder's application12
Typical time from launch to 100% structure4 years 8 months
MahaRERA complaints (filed by or against the builder), all Gokhale Constructions projects12 (6 of 23 projects)
What these mean
  • Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
  • Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
  • Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
  • Under construction: MahaRERA status Active.
  • Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
  • Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
  • MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.

Where they build: Kothrud (5) · Bopodi (1) · Shukrawar Peth (1) · Parvati (1)

Under construction

ProjectVillageStagePossessionBooked
ManodeepKothrudEarly stageMay 20297 units booked out of total 9 units
NiwantShukrawar PethReady to moveSeptember 202611 units booked out of total 14 units
Shree Ganesh Park ChslKothrudEarly stageOctober 203118 units booked out of total 27 units
Tejalkunj No.2KothrudNearing possessionJune 202765 units booked out of total 69 units
UmaParvatiEarly stageJune 20283 units booked out of total 12 units
Completed
ProjectVillageStatus
90 MadhukunjBopodiCompleted
AyodhyanagarKothrudCompleted
Gokhale Business BayKothrudCompleted
MalkansKothrudCompleted
ManikErandwaneCompleted
Pooja RajasKothrudCompleted
RahulkunjKothrudCompleted
SaloniErandwaneCompleted
Saraswati ParkKothrudCompleted
Shashi MadhavBavdhan KhurdCompleted
Sulabh MonaliErandwaneCompleted
SwastishreeAundhCompleted
VandanshreeKothrudCompleted
WavesWakadCompleted
ZelamErandwaneCompleted
Lapsed
ProjectVillageStatus
PushpakunjKothrudLapsed
Shreekunj ShreeKothrudLapsed

Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.