Guardian projects in Pune
MahaRERA projects by Guardian registered 2017–2021 in Pune & PCMC.
| Projects registered with MahaRERA | 10 |
|---|---|
| Total units across these projects | 1,736 |
Full record
MahaRERA projects registered 2017–2021 in Pune & PCMC
| Completed without extending the possession date | 1 |
|---|---|
| Completed after an extension | 1 |
| Lapsed | 5 |
| Under construction | 2 |
| Not updated on MahaRERA for over a year | 1 |
| Possession date extended on the builder's application | 6 |
| MahaRERA complaints (filed by or against the builder), all Guardian projects | 41 (6 of 10 projects) |
What these mean
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
- Not updated on MahaRERA for over a year: the builder has not filed an update with MahaRERA for more than a year, so FlatNama cannot show a current status.
Where they build: Wagholi (1) · Parvati (1)
Under construction
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| Guardian Cityscapes · 2 phases | Parvati | Ready to move | Oct 2027 | 195 units booked out of total 327 units |
| Guardian Eastern Meadows - Phase 2 | Wagholi | Nearing possession | April 2027 | 148 units booked out of total 227 units |
Completed
| Project | Village | Status |
|---|---|---|
| Guardian Cityscapes | Parvati | Completed |
Lapsed
| Project | Village | Status |
|---|---|---|
| Guardian Anantam | Kondhwa Budruk | Lapsed |
| Guardian Eastern Meadows | Wagholi | Lapsed |
| Guardian Wind Shire | Kirkatwadi | Lapsed |
| Hill Shire | Wagholi | Lapsed |
Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.