Kunal projects in Pune
MahaRERA projects by Kunal registered 2017–2020 in Pune & PCMC.
| Projects registered with MahaRERA | 8 |
|---|---|
| Total units across these projects | 842 |
Full record
MahaRERA projects registered 2017–2020 in Pune & PCMC
| Completed without extending the possession date | 7 |
|---|---|
| Completed after an extension | 0 |
| Lapsed | 1 |
| Under construction | 0 |
| Possession date extended on the builder's application | 0 |
| MahaRERA complaints (filed by or against the builder), all Kunal projects | 0 (0 of 8 projects) |
What these mean
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Completed
| Project | Village | Status |
|---|---|---|
| ICONIA | Ravet | Completed |
| Kunal Aspiree | Baner | Completed |
| Kunal Iconia -commercial | Ravet | Completed |
Lapsed
| Project | Village | Status |
|---|---|---|
| ICONIA | Ravet | Lapsed |
Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.
Is a project grouped wrongly or a figure out of date? Tell us