Naiknavare projects in Pune
MahaRERA projects by Naiknavare registered 2017–2026 in Pune & PCMC.
| Projects registered with MahaRERA | 15 |
|---|---|
| Total units across these projects | 1,134 |
Full record
MahaRERA projects registered 2017–2026 in Pune & PCMC
| Completed without extending the possession date | 2 |
|---|---|
| Completed after an extension | 6 |
| Lapsed | 3 |
| Under construction | 4 |
| Possession date extended on the builder's application | 9 |
| Typical time from launch to 100% structure | 3 years 8 months |
| MahaRERA complaints (filed by or against the builder), all Naiknavare projects | 7 (3 of 15 projects) |
What these mean
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Where they build: Aundh (1) · Talegaon Dabhade (1) · Erandwane (1) · Sadashiv Peth (1) · Wadgaon Maval (1) · Shivajinagar (1)
Under construction
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| Centralvista | Sadashiv Peth | Mid-construction | December 2030 | 21 units booked out of total 300 units |
| Kutumb Woods | Wadgaon Maval | Early stage | April 2029 | 1 unit booked out of total 62 units |
| Shridhar Bhalchandra | Shivajinagar | Early stage | December 2029 | 15 units booked out of total 28 units |
Completed
| Project | Village | Status |
|---|---|---|
| Eminence Project 1 | Lohegaon | Completed |
| Neelaya | Talegaon Dabhade | Completed |
| Seasons Business Square | Aundh | Completed |
| Shivatman | Erandwane | Completed |
| Sylvan Heights H | Aundh | Completed |
| The Spires | Aundh | Completed |
Lapsed
| Project | Village | Status |
|---|---|---|
| 7 Business Square | Yerwada | Lapsed |
| Eminence Project 2 | Lohegaon | Lapsed |
| Kutumb Prime Project 6 | Talegaon Dabhade | Lapsed |
Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.
Is a project grouped wrongly or a figure out of date? Tell us