NG Rathi projects in Pune

MahaRERA projects by NG Rathi registered 2017–2026 in Pune & PCMC.

Projects registered with MahaRERA14
Total units across these projects1,709
Full record

MahaRERA projects registered 2017–2026 in Pune & PCMC

Completed without extending the possession date3
Completed after an extension2
Lapsed4
Under construction5
Possession date extended on the builder's application7
Typical time from launch to 100% structure6 years 3 months
MahaRERA complaints (filed by or against the builder), all NG Rathi projects10 (5 of 14 projects)
What these mean
  • Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
  • Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
  • Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
  • Under construction: MahaRERA status Active.
  • Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
  • Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
  • MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.

Where they build: Wagholi (2) · Pirangut (2) · Yerwada (1) · Vishrantwadi (1) · Undri (1)

Under construction

ProjectVillageStagePossessionBooked
Hillcrest ManorUndriEarly stageSeptember 20290 units booked out of total 18 units
MadhubanPirangutNearing possessionDecember 2026207 units booked out of total 208 units
Madhuban Phase IIPirangutEarly stageDecember 20280 units booked out of total 133 units
NandanvanVishrantwadiMid-constructionDecember 202883 units booked out of total 193 units
Serene SpacesWagholiEarly stageApril 20300 units booked out of total 38 units
Completed
ProjectVillageStatus
BlossomWagholiCompleted
Palm NestWagholiCompleted
PalmnestWagholiCompleted
SierraUndriCompleted
UrbanoWagholiCompleted
Lapsed
ProjectVillageStatus
BenchmarkMohammadwadiLapsed
Palm NestWagholiLapsed
PalmnestWagholiLapsed
Vrundavan AYerwadaLapsed

Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.