Saarrthi projects in Pune

MahaRERA projects by Saarrthi registered 2017–2024 in Pune & PCMC.

Projects registered with MahaRERA14
Total units across these projects2,115
Full record

MahaRERA projects registered 2017–2024 in Pune & PCMC

Completed without extending the possession date3
Completed after an extension5
Lapsed3
Under construction3
Possession date extended on the builder's application11
Typical time from launch to 100% structure6 years 2 months
MahaRERA complaints (filed by or against the builder), all Saarrthi projects29 (9 of 14 projects)
What these mean
  • Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
  • Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
  • Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
  • Under construction: MahaRERA status Active.
  • Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
  • Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
  • MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.

Where they build: Mahalunge (2)

Under construction

ProjectVillageStagePossessionBooked
Saarrthi Skybay IIIMahalungeNearing possessionDecember 2026306 units booked out of total 318 units
Saarrthi SkybizzMahalungeNearing possessionMarch 2027204 units booked out of total 263 units
Completed
ProjectVillageStatus
Saarrthi Savvy HomesHinjewadiCompleted
Saarrthi SerenityKothrudCompleted
Saarrthi ShivalikKothrudCompleted
Saarrthi SkybayMahalungeCompleted
SpectraKothrudCompleted
StanzaPunawaleCompleted
Success SquareShivajinagarCompleted
West SquareWadgaon BudrukCompleted
Lapsed
ProjectVillageStatus
Saarrthi Savvy Homes IIHinjewadiLapsed
Saarrthi Skybay IIBanerLapsed
SignatureShivajinagarLapsed

Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.

Is a project grouped wrongly or a figure out of date? Tell us