Shakuntal projects in Pune
MahaRERA projects by Shakuntal registered 2017–2026 in Pune & PCMC.
| Projects registered with MahaRERA | 12 |
|---|---|
| Total units across these projects | 1,666 |
Full record
MahaRERA projects registered 2017–2026 in Pune & PCMC
| Completed without extending the possession date | 0 |
|---|---|
| Completed after an extension | 0 |
| Lapsed | 4 |
| Under construction | 7 |
| Not updated on MahaRERA for over a year | 1 |
| Possession date extended on the builder's application | 4 |
| Typical time from launch to 100% structure | 1 year |
| MahaRERA complaints (filed by or against the builder), all Shakuntal projects | 0 (0 of 12 projects) |
What these mean
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
- Not updated on MahaRERA for over a year: the builder has not filed an update with MahaRERA for more than a year, so FlatNama cannot show a current status.
Where they build: Narayan Peth (1) · Dudulgaon (1) · Wagholi (1) · Chikhali (1) · Parvati (1) · Manjari Budruk (1) · Sadashiv Peth (1) · Chovisawadi (1)
Under construction
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| Dwarka Blue Water | Chikhali | Mid-construction | May 2031 | 40 units booked out of total 296 units |
| Prince Plaza | Wagholi | Nearing possession | June 2028 | 11 units booked out of total 15 units |
| Shakuntal Alentia Phase - I | Chovisawadi | Early stage | May 2031 | 17 units booked out of total 397 units |
| Shakuntala | Parvati | Nearing possession | June 2027 | 13 units booked out of total 18 units |
| Shakuntala | Sadashiv Peth | Early stage | December 2028 | 14 units booked out of total 18 units |
| Shakuntala Sankul | Manjari Budruk | Mid-construction | May 2028 | 0 units booked out of total 48 units |
Lapsed
| Project | Village | Status |
|---|---|---|
| Forestia | Moshi | Lapsed |
| Forestia | Dudulgaon | Lapsed |
| Nitya Residency | Narayan Peth | Lapsed |
| Shakuntal Dwarka | Chikhali | Lapsed |
Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.
Is a project grouped wrongly or a figure out of date? Tell us